November 16, 2006   The main alternator final installation fabrication

November 6, 2006   The main alternator magneto drive engine coupling final fit test and welding

November 4, 2006   The main alternator magneto drive engine coupling final machining

October 5, 2006   The main alternator magneto drive engine coupling initial machining

November 30, 2003   The main alternator now fits in the magneto drive

August 30, 2003   Progress is made on the fuel injection system installation

August 13, 2003   The alternator is in place

August 2, 2003   The Bosch CIS Fuel Injection system has been found and procured

July 7, 2003   The turbo exhaust flange, stack and tailpipe are fabricated

June 3, 2003   The fuel injection is gone and it's time to mount the carb?

May 10, 2003   The turbo oil feed and cooling air feed fittings and lines are installed

April 29, 2003   The cowl flap design mock up begins

April 18, 2003   Air cooling for the ignition coil pack and running high tension cables

April 12, 2003   Air cooling manifold for second dynamo regulator

April 2, 2003   Air cooling manifold for dynamo regulator

March 31, 2003   Oil cooler ducting is complete

March 20, 2003   Oil cooler duct installation clip and top cowling finishing issues

March 7, 2003   Oil cooler duct is fiberglassed and top cowling is taking shape

March 1, 2003   Engine baffle seals and oil cooler inlet ducting

February 24, 2003   Rear engine baffle

February 18, 2003   Intercooler leak discovered

February 11, 2003   Engine baffles continued

January 20, 2003   Engine baffles for the cylinder heads and cylinders 

December 2,  2002   Engine baffles for the cylinder heads

November 27,  2002   Engine baffles with aluminum

November 16,  2002   Engine baffles begin with poster board patterns

October 25,  2002   Air-Oil-Separator and Oil Cooler completed

October 20,  2002   Air-Oil-Separator construction

October 9,  2002   Oil Cooler mounting bracket machining complete.

September 26,  2002   Oil Cooler mounted on the firewall.

September 23,  2002   First pass on weight and balance.

September 11,  2002   Turbo oil drain line connected to scavenge oil pump.

September 3,  2002   The intercooler is mounted to the engine as it will fly.

September 2,  2002   Right intercooler end cap and exit pipe are welded on.

September 1,  2002   Digital photography test

August 29, 2002   Fitting the right intercooler end cap and exit tube.

August 22, 2002   I've finally welded the intercooler core to the left end cap.

August 13, 2002   I'm back from SportAir welding school and making progress on the intercooler.

August 2, 2002    I give up, I'm going to school to learn how to weld.

July 13, 2002      Intercooler fabrication.

July 6, 2002        Fabrication of the bottom cooling duct diffuser.

June 17, 2002    Bottom cooling design breakthrough; conical diffuser then transition duct from round to rectangle

June 10, 2002    Bottom cooling design coming together (inter-cooler and oil-cooler installation)

June 4, 2002      Oil cooler block off plate installation resolved

May 27,2002       Oil cooler block off plate manufacture woes continue

May 14, 2002      Oil cooler block off plate manufacture woes

May 1, 2002         Exhaust system finally completed